Skip to content
Kaulii

RPT-90067

Pacific Fiber Solutions · Fiber · WO-24371

71

out of 100

Proof Score™

Acceptable

Documentation quality for Fiber Drop Installation

Processing58% evidence completeGenerated by Jamal Whitfield
Video clarity
GPS verified
Timestamp verified
Technician identified
Work order identified
Installation clearly visible
Safety equipment documented
Equipment documented
Serial numbers captured
Before/After evidence
Work explanation
Recommended follow-up included

Missing evidence

  • Portions of the footage are motion-blurred and unusable as evidence.
  • GPS unavailable — location could not be confirmed from the capture device.
  • Capture timestamp could not be verified against device metadata.
  • Technician never stated their name on the recording.
  • Narration does not explain what work was actually completed.

AI recommendations

  • Re-record the unclear segments with the camera held steady for 5 seconds per shot.
  • Enable location services on the capture device before recording.
  • Record directly in the app so the timestamp is signed at capture.
  • State your full name and role in the first 10 seconds.
  • Add 20 seconds of plain-language narration describing the completed work.
Executive summary

Fiber work at 4129 Marlow Ave, Sacramento, CA was completed and documented on site by Jamal Whitfield. The technician captured a narrated walkthrough of the finished installation, confirmed all connections and equipment were in working order, and verified the work area was cleaned and secured before departure. A small number of evidence gaps were detected and are listed below.

Work completed
  • Completed Fiber Drop Installation at 4129 Marlow Ave, Sacramento, CA
  • Pulled and secured the fiber drop from the pedestal to the demarcation point
  • Fusion spliced the strands and seated them in a protected splice tray
  • OTDR tested the span end to end and recorded loss values on video
  • Labeled the drop, sealed the enclosure and restored the work area
  • Work area cleaned, debris removed and site secured
  • Customer walkthrough narrated on camera for approval
Materials mentioned
  • Single-mode drop cable
  • Fusion splice sleeves
  • Weatherproof splice enclosure
  • Cable ties and drop clamps
  • Labeling and identification tags
Equipment identified
  • Fusion splicer
  • OTDR and optical power meter
  • Fiber cleaver and cleaning kit
  • Kaulii mobile capture — GPS and timestamp signed at recording
Safety observations
  • Lockout/tagout applied before any energized or pressurized work
  • PPE worn throughout — eye protection, gloves, hard hat where required
  • Work zone barricaded and signage posted
  • Area cleared and secured before departure
Issues found
  • LowExisting pedestal seal is degraded and allows moisture intrusion — noted for monitoring only.
Recommended follow-up
  1. 1Schedule a follow-up inspection within 90 days.
  2. 2Add this asset to the preventative maintenance rotation.
  3. 3Share this report with the property contact for approval.
Technician statement

Alright, this is work order WO-24371. My name is Jamal Whitfield with Pacific Fiber Solutions. I'm at 4129 Marlow Ave, Sacramento, CA for Fiber Drop Installation. I'm going to walk you through the completed work now. Here's the finished installation — you can see everything is mounted level and secured. Walking around the left side, all the connections are torqued and labeled. Here's the main equipment, and I'm getting a close-up of the nameplate so you have the model and serial on file. Safety-wise, I had lockout applied the whole time I was in the panel, PPE on, and the area was taped off. As far as the work completed, we handled the full fiber scope, tested everything, and it's reading in range. One thing I did run into was some wear on the adjacent equipment — nothing that affects today's work but worth watching. For follow-up, I'd recommend an inspection in about 90 days. Here's a final overview of the completed job, cleaned up and ready for the customer. That's it for work order WO-24371.

Evidence gallery
Supervisor review
Documentation qualityAcceptable
Evidence completeness58%
Customer readyNO
Claim readyNO
Warranty readyNO
Audit readyNO
Supervisor confidenceLow
Timeline
Recording date2026-07-22
Time10:53 AM CDT
Recording duration5m 33s
Report generated2026-07-22 · report built in 47 seconds
Work orderWO-24371
CompanyPacific Fiber Solutions

30.2433° N, 97.7633° W

4129 Marlow Ave, Sacramento, CA

Timestamp verified at capture

Scan to open the live online version of this report. Included on the branded PDF.