Gas work at 4407 Grand Ave, Minneapolis, MN was completed and documented on site by Anthony Walker. The technician captured a narrated walkthrough of the finished installation, confirmed all connections and equipment were in working order, and verified the work area was cleaned and secured before departure. All required evidence for customer approval, warranty and audit was captured.
- Completed Gas Line Repair at 4407 Grand Ave, Minneapolis, MN
- Shut off and locked out the service before beginning work
- Installed the meter set and regulator with correct clearances
- Leak tested all joints with soap solution and a calibrated detector
- Relit and verified appliance operation before leaving the site
- Work area cleaned, debris removed and site secured
- Customer walkthrough narrated on camera for approval
- Gas meter and regulator
- Yellow coated service piping
- Approved thread sealant
- Riser supports and bollard hardware
- Labeling and identification tags
- Combustible gas detector
- Manometer
- Pipe wrenches and threading dies
- Kaulii mobile capture — GPS and timestamp signed at recording
- Lockout/tagout applied before any energized or pressurized work
- PPE worn throughout — eye protection, gloves, hard hat where required
- Work zone barricaded and signage posted
- Area cleared and secured before departure
- LowService riser coating is chipped at grade and should be recoated — noted for monitoring only.
- 1Schedule a follow-up inspection within 90 days.
- 2Add this asset to the preventative maintenance rotation.
- 3Share this report with the property contact for approval.
Alright, this is work order WO-24174. My name is Anthony Walker with Northstar Utilities. I'm at 4407 Grand Ave, Minneapolis, MN for Gas Line Repair. I'm going to walk you through the completed work now. Here's the finished installation — you can see everything is mounted level and secured. Walking around the left side, all the connections are torqued and labeled. Here's the main equipment, and I'm getting a close-up of the nameplate so you have the model and serial on file. Safety-wise, I had lockout applied the whole time I was in the panel, PPE on, and the area was taped off. As far as the work completed, we handled the full gas scope, tested everything, and it's reading in range. One thing I did run into was some wear on the adjacent equipment — nothing that affects today's work but worth watching. For follow-up, I'd recommend an inspection in about 90 days. Here's a final overview of the completed job, cleaned up and ready for the customer. That's it for work order WO-24174.
30.2585° N, 97.7785° W
4407 Grand Ave, Minneapolis, MN
Timestamp verified at capture