Pacific Fiber Solutions · Telecom · WO-24147
77
out of 100
Proof Score™
Acceptable
Documentation quality for Cabinet Node Installation
Missing evidence
- ⚠ Portions of the footage are motion-blurred and unusable as evidence.
AI recommendations
- “Re-record the unclear segments with the camera held steady for 5 seconds per shot.”
Telecom work at 3737 Sunrise Way, Sacramento, CA was completed and documented on site by Dana Whitfield. The technician captured a narrated walkthrough of the finished installation, confirmed all connections and equipment were in working order, and verified the work area was cleaned and secured before departure. A small number of evidence gaps were detected and are listed below.
- Completed Cabinet Node Installation at 3737 Sunrise Way, Sacramento, CA
- Inspected and serviced the cabinet node and verified power to all cards
- Cleaned optical connectors and reseated jumper terminations
- Confirmed signal levels and alarm clearance with the network operations center
- Secured the cabinet and documented the final configuration
- Work area cleaned, debris removed and site secured
- Customer walkthrough narrated on camera for approval
- Optical jumpers
- Rack hardware and cable management
- Desiccant and cabinet seals
- Port labels
- Labeling and identification tags
- Optical power meter
- Laptop with craft interface
- Torque driver and connector cleaning kit
- Kaulii mobile capture — GPS and timestamp signed at recording
- Lockout/tagout applied before any energized or pressurized work
- PPE worn throughout — eye protection, gloves, hard hat where required
- Work zone barricaded and signage posted
- Area cleared and secured before departure
- LowCabinet cooling fan is running intermittently and should be replaced — noted for monitoring only.
- 1Schedule a follow-up inspection within 90 days.
- 2Add this asset to the preventative maintenance rotation.
- 3Share this report with the property contact for approval.
Alright, this is work order WO-24147. My name is Dana Whitfield with Pacific Fiber Solutions. I'm at 3737 Sunrise Way, Sacramento, CA for Cabinet Node Installation. I'm going to walk you through the completed work now. Here's the finished installation — you can see everything is mounted level and secured. Walking around the left side, all the connections are torqued and labeled. Here's the main equipment, and I'm getting a close-up of the nameplate so you have the model and serial on file. Safety-wise, I had lockout applied the whole time I was in the panel, PPE on, and the area was taped off. As far as the work completed, we handled the full telecom scope, tested everything, and it's reading in range. One thing I did run into was some wear on the adjacent equipment — nothing that affects today's work but worth watching. For follow-up, I'd recommend an inspection in about 90 days. Here's a final overview of the completed job, cleaned up and ready for the customer. That's it for work order WO-24147.
30.2473° N, 97.7673° W
3737 Sunrise Way, Sacramento, CA
Timestamp verified at capture