RPT-90436
Redline HVAC · HVAC · WO-24002
93
out of 100
Proof Score™
Excellent
Documentation quality for Rooftop Unit Service
Missing evidence
- ⚠ Final installation overview missing.
AI recommendations
- “Record a wider overview of the completed installation.”
HVAC work at 3027 Ashland Ave, Dallas, TX was completed and documented on site by Logan Fitzgerald. The technician captured a narrated walkthrough of the finished installation, confirmed all connections and equipment were in working order, and verified the work area was cleaned and secured before departure. A small number of evidence gaps were detected and are listed below.
- Completed Rooftop Unit Service at 3027 Ashland Ave, Dallas, TX
- Recovered refrigerant and removed the failed unit from the curb
- Set, sealed and secured the replacement unit to the existing curb
- Reconnected power, controls, condensate and gas where applicable
- Charged, started up and verified supply-return split under load
- Work area cleaned, debris removed and site secured
- Customer walkthrough narrated on camera for approval
- Packaged rooftop unit
- Curb adapter and gasket
- Refrigerant and filter drier
- Control wiring and whip
- Labeling and identification tags
- Refrigerant gauges and recovery machine
- Digital thermometer and anemometer
- Crane or boom lift
- Kaulii mobile capture — GPS and timestamp signed at recording
- Lockout/tagout applied before any energized or pressurized work
- PPE worn throughout — eye protection, gloves, hard hat where required
- Work zone barricaded and signage posted
- Area cleared and secured before departure
- MediumCondenser fan blade shows early corrosion pitting on two blades.
- LowAccess panel hardware is worn and should be replaced at next visit.
- 1Schedule a follow-up inspection within 90 days.
- 2Add this asset to the preventative maintenance rotation.
- 3Share this report with the property contact for approval.
Alright, this is work order WO-24002. My name is Logan Fitzgerald with Redline HVAC. I'm at 3027 Ashland Ave, Dallas, TX for Rooftop Unit Service. I'm going to walk you through the completed work now. Here's the finished installation — you can see everything is mounted level and secured. Walking around the left side, all the connections are torqued and labeled. Here's the main equipment, and I'm getting a close-up of the nameplate so you have the model and serial on file. Safety-wise, I had lockout applied the whole time I was in the panel, PPE on, and the area was taped off. As far as the work completed, we handled the full hvac scope, tested everything, and it's reading in range. One thing I did run into was some wear on the adjacent equipment — nothing that affects today's work but worth watching. For follow-up, I'd recommend an inspection in about 90 days. Here's a final overview of the completed job, cleaned up and ready for the customer. That's it for work order WO-24002.
30.2572° N, 97.7772° W
3027 Ashland Ave, Dallas, TX
Timestamp verified at capture
Scan to open the live online version of this report. Included on the branded PDF.