RPT-91104
Summit Electrical Group · Electrical · WO-24210
97
out of 100
Proof Score™
Excellent
Documentation quality for Traffic Signal Repair
Missing evidence
- ⚠ Work order number was not spoken or shown on camera.
AI recommendations
- “Say the work order number out loud at the start of the walkthrough.”
Electrical work at 8465 Brighton Blvd, Denver, CO was completed and documented on site by Chris Miller. The technician captured a narrated walkthrough of the finished installation, confirmed all connections and equipment were in working order, and verified the work area was cleaned and secured before departure. A small number of evidence gaps were detected and are listed below.
- Completed Traffic Signal Repair at 8465 Brighton Blvd, Denver, CO
- Isolated the feeder and verified zero energy before opening the enclosure
- Replaced failed components and re-landed conductors on labeled terminations
- Performed insulation resistance and continuity testing on affected circuits
- Restored power and confirmed balanced phase loading at the panel
- Work area cleaned, debris removed and site secured
- Customer walkthrough narrated on camera for approval
- Breakers and terminal lugs
- THHN conductor and conduit fittings
- Panel schedule labels
- Anti-oxidant compound
- Labeling and identification tags
- Insulation resistance tester
- Clamp meter and thermal camera
- Torque screwdriver set
- Kaulii mobile capture — GPS and timestamp signed at recording
- Lockout/tagout applied before any energized or pressurized work
- PPE worn throughout — eye protection, gloves, hard hat where required
- Work zone barricaded and signage posted
- Area cleared and secured before departure
- MediumAdjacent breaker shows heat discoloration and should be evaluated at the next service window.
- LowAccess panel hardware is worn and should be replaced at next visit.
- 1Schedule a follow-up inspection within 90 days.
- 2Add this asset to the preventative maintenance rotation.
- 3Share this report with the property contact for approval.
Alright, this is work order WO-24210. My name is Chris Miller with Summit Electrical Group. I'm at 8465 Brighton Blvd, Denver, CO for Traffic Signal Repair. I'm going to walk you through the completed work now. Here's the finished installation — you can see everything is mounted level and secured. Walking around the left side, all the connections are torqued and labeled. Here's the main equipment, and I'm getting a close-up of the nameplate so you have the model and serial on file. Safety-wise, I had lockout applied the whole time I was in the panel, PPE on, and the area was taped off. As far as the work completed, we handled the full electrical scope, tested everything, and it's reading in range. One thing I did run into was some wear on the adjacent equipment — nothing that affects today's work but worth watching. For follow-up, I'd recommend an inspection in about 90 days. Here's a final overview of the completed job, cleaned up and ready for the customer. That's it for work order WO-24210.
30.2568° N, 97.7768° W
8465 Brighton Blvd, Denver, CO
Timestamp verified at capture
Scan to open the live online version of this report. Included on the branded PDF.